Question
On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress)
On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 40% of direct materials costs. During the month, the jobs used direct materials as shown below.
Job 1 | Job 2 | Job 3 | |||||||
Direct materials used | $ | 5,000 | $ | 7,000 | $ | 1,500 | |||
During the month, the jobs used direct labor as shown below. Jobs 1 and 3 are not finished by the end of March, and Job 2 is finished but not sold by the end of March.
Job 1 | Job 2 | Job 3 | |||||||
Direct labor used | $ | 9,000 | $ | 4,000 | $ | 3,000 | |||
1. Determine the amounts of direct materials, direct labor, and factory overhead applied that would be reported on job cost sheets for each of the three jobs for March. 2. Determine the total dollar amount of Work in Process Inventory at the end of March. 3. Determine the total dollar amount of Finished Goods Inventory at the end of March. Assume the company has no beginning Work in Process or Finished Goods inventories.
JOB COST SHEET Job 1 $ 5,000 $ 9,000 Job 2 7,000 4,000 $ Job 3 1,500 3,000 Direct materials Direct labor Factory overhead Total $ 14,000 $ 11,000 $ 4,500 Ending work in process inventory Finished goods inventoryStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started