Question

1 Approved Answer

A small assembly line for the assembly of power steering pumps needs to be balanced. Precedence diagram is shown below. 0.4 A 0.6 B

 

A small assembly line for the assembly of power steering pumps needs to be balanced. Precedence diagram is shown below. 0.4 A 0.6 B % Station 1 2 3 What is the assembly-line efficiency? Round your answer to one decimal place. 0.4 The cycle time is determined to be 2.0 minutes. How would the line be balanced by choosing the assignable task having the longest task time first? Fill in the table below. If your answer is zero, enter "O". Round your answers to one decimal place. Tasks B,A,C,D E,F G,H,I Total 0.2 D 0.7 0.8 (H 0.4 Total Time 0.3 Idle Time

Step by Step Solution

3.41 Rating (151 Votes )

There are 3 Steps involved in it

Step: 1

Total time Sum of task time Idle time Cycle time Total time 22 Total time Statio... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

CFIN

Authors: Scott Besley, Eugene Brigham

5th edition

1305661656, 9781305888036 , 978-1305666870

More Books

Students also viewed these Mathematics questions