On September 1, two jobs were in process at Petes Patios. Details of the jobs follow: Job Number Direct Materials Direct Labor PP-24 $ 1,064

On September 1, two jobs were in process at Petes Patios. Details of the jobs follow:

Job Number Direct Materials Direct Labor
PP-24 $ 1,064 $ 354
PP-30 555 1,630

Materials Inventory on September 1 totaled $5,500, and $662 worth of materials was purchased during the month. Indirect materials of $106 were withdrawn from materials inventory. On September 1, finished goods inventory consisted of two jobs, PP-12, costing $2,270, and PP-14, with a cost of $946. Costs for both jobs were transferred to Cost of Services Billed during the month.

Also during September, Jobs PP-24 and PP-30 were completed. Completing Job PP-24 required an additional $1,400 in direct labor. The completion costs for Job PP-30 included $640 in direct materials and $4,300 in direct labor.

Petes Patios used a total of $1,884 of direct materials (excluding the $106 indirect materials) during the period, and total direct labor costs during the month amounted to $8,190. Overhead has been estimated at 50 percent of direct labor costs, and this relation has been the same for the past few years.

Required:

Compute the costs to Jobs PP-24 and PP-30 and the balances in the September 30 inventory accounts.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions