On the basis of the project described by the following set of activities answer the following questions: Activity Activity Predecessor Time (weeks) 1 3

On the basis of the project described by the following set of activities answer the following questions:
ActivityActivity PredecessorTime (weeks)
13
27
312
425
526
641
754

(a1)

Your answer is correct.
Select a Gantt chart for the project described above.

LINK TO TEXT

Attempts: 1 of 15 used

(a2)

For the project described above indicate the project completion time.
Project completion time

weeks
Indicate the available slack for each activity.
ActivitySlack (weeks)
1

2

3

4

5

6

7

Step by Step Solution

3.42 Rating (152 Votes )

There are 3 Steps involved in it

Step: 1

EF calculated using the forward pass 1 2 and ES 0 because 1 2 have no precursor Since 1 is 3s ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management The Managerial Process

Authors: Erik W. Larson, Clifford F. Gray

7th edition

1260547272, 1259666093, 9781260547276, 978-1259666094

More Books

Students also viewed these Accounting questions