On the bill for a Time & Materials contract, you see the following line items. LABOR Labor Category Labor Rate Hours Used Designer $200/hour 100
- On the bill for a Time & Materials contract, you see the following line items.
LABOR | ||
Labor Category | Labor Rate | Hours Used |
Designer | $200/hour | 100 |
Architect | $300/hour | 200 |
Engineer | $250/hour | 400 |
MATERIALS | ||
Item | Cost | Fee |
Building Materials | $300,000 | 5% |
Tools | $200,000 | -- |
Vehicle Rental | $50,000 | 2% |
How much does your project owe? (5 points)