onathan wants to know the longest time path taken to complete a project. He defines the activities and assigns time estimates to each activity. He
onathan wants to know the longest time path taken to complete a project. He defines the activities and assigns time estimates to each activity. He also assigns cost estimates to each activity. Which of the following methods is Jonathan using? Group of answer choices A Pareto chart A program evaluation and review technique (PERT) chart A fishbone diagram A Gantt chart
Step by Step Solution
There are 3 Steps involved in it
Step: 1