Once the network schedule is created and the critical path is identified, the project manager should basically monitor only critical path tasks, since delays and
Once the network schedule is created and the critical path is identified, the project manager should basically monitor only critical path tasks, since delays and problems in non-critical path activities are of no consequence to the overall project schedule. Group of answer choices True False