Once you have created your WBS in MS Project, creating the schedule is relatively easy. Basically, beginning with each work package in the WBS ,

Once you have created your WBS in MS Project, creating the schedule is relatively easy.
Basically, beginning with each work package in the WBS, you must add the following in MS Project.
1. Each task (work package) should be linked to its PREDECESSOR and SUCCESSOR tasks. That is, you know you cannot start on the task until predecessor tasks are completed. Each predecessor/successor must be identified in MS Project.
2. Each task should be assigned a duration. That is, how long will it take to complete this task. This can be entered in minutes, hours or days. But you must use the same timeframe for all tasks in your plan.
3. Each task should be assigned a start date.
Once these items have been entered into MS Project, it will automatically draw your Network Activity Diagram project schedule for you. And, the it will ALSO draw the GANTT chart for you. So if you use MS Project to complete THIS assignment for you, you will pretty much be done with the NEXT assignment as well.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Exploring Management

Authors: John R. Schermerhorn

3rd edition

1118217252, 9780470878217, 978-1118217252

More Books

Students also viewed these General Management questions