One of the purposes of project integration is to maintain a balance between priorities and constraints associated with the other knowledge areas. True False The
- One of the purposes of project integration is to maintain a balance between priorities and constraints associated with the other knowledge areas.
- True
- False
- ThePerform Integrated Change Controlprocess monitors the performance of the project against plan
- True
- False
- The project management plan could contain which of the following
- Scope baseline
- Schedule baseline
- Cost baseline
- All of the above
- Which of the following is an output of Direct and Manage Project Work?
- Deliverables
- Cost baseline
- Charter
- Stakeholder requirements
- Work performance reports are an output of Monitor and Control Project Work
- True
- False
- Which of the following could be an output of Close Project or Phase?
- Accepted deliverables
- Organization process assets updates
- Approved change requests
- Issue log
- Approved change requests can be an output of Monitor and Control Project Work
- True
- False
- Expert judgment is a tool and technique in all seven Project Integration Management processes
- True
- False
- In which process is the Project Management Information System most heavily used?
- Develop Project Charter
- Develop Project Management Plan
- Close Project or Phase
- Direct and Manage Project Work
- In which process is the lessons learned register created?
- Close Project or Phase
- Develop Project Charter
- Perform Integrated Change Control
- Manage Project Knowledge
- In which process is the lessons learned repository updated?
- Develop project charter
- Develop project management plan
- Close project or phase
- Manage project knowledge
- The issue log is created in which process?
- Manage project knowledge
- Direct and manage project work
- Develop project management plan
- Perform integrated change control
- Accepted deliverables are an output of which process?
- Validate scope
- Control quality
- Direct and manage project work
- All of the above
- A Change Control Board may be instituted in which process?
- Monitor and control project work
- Manage project knowledge
- Develop project charter
- Perform integrated change control
- Which of the following processes is most likely to use focus groups and storytelling?
- Develop project charter
- Manage project knowledge
- Develop project management plan
- Perform integrated change control
- The project charter can contain information which links the project to strategic objectives
- True
- False
- The project management plan unifies outputs of the planning processes
- True
- False
- Accepted deliverables are an input to Close Project or Phase
- True
- False
- The change control board is utilized in the Monitor and Control Project Work process
- True
- False
- The Manage Project Knowledge process can directly generate corrective action needed to help a project execute per its project management plan
- True
- False
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started