One of your project manager sends you a project finance summary as follows: Budgeted Cost till date $ 4 0 K , Actual Cost $
One of your project manager sends you a project finance summary as follows: Budgeted Cost till date $K Actual Cost $K Budget at Completion is $K and the EAC is $K She feels that the project is Green from Cost Management perspective. Your Program Controller says that Earned Value is $K With this information, your conclusion would be:
SELECT THE CORRECT ANSWER
Concur with the Project Manager
Project is RED, as it would have no $ to complete the remaining work
Alert the Sponsor about the possible overrun
Rework the business case assuming another overrun given her track record
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started