Question

1 Approved Answer

One of your project manager sends you a project finance summary as follows: Budgeted Cost till date $ 4 0 K , Actual Cost $

One of your project manager sends you a project finance summary as follows: Budgeted Cost till date $40K, Actual Cost $45K, Budget at Completion is $100K, and the EAC is $105K. She feels that the project is Green from Cost Management perspective. Your Program Controller says that Earned Value is $30K. With this information, your conclusion would be:
SELECT THE CORRECT ANSWER
Concur with the Project Manager
Project is RED, as it would have no $ to complete the remaining work
Alert the Sponsor about the possible overrun
Rework the business case assuming another 10% overrun given her track record

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction to Management Science

Authors: Bernard W. Taylor

11th Edition

132751917, 978-0132751919

More Books

Students also viewed these General Management questions