Question

1 Approved Answer

One of your Taiwanese suppliers has bid on a new line of molded plastic parts that is currently being assembled at your plant. The supplier

One of your Taiwanese suppliers has bid on a new line of molded plastic parts that is currently being assembled at your plant. The supplier has bid $0.10 per part, given a forecast you provided of 200,000 parts in year 1; 400,000 in year 2; and 600,000 in year 3. Shipping and handling of parts from the suppliers factory is estimated at $0.01 per unit. Additional inventory handling charges should amount to $0.004 per unit. Finally, administrative costs are estimated at $30 per month.
Although your plant is able to continue producing the part, the plant would need to invest in another molding machine, which would cost $20,000. Direct materials can be purchased for $0.06 per unit. Direct labor is estimated at $0.04 per unit for wages plus a 50 percent surcharge for benefits and, indirect labor is estimated at $0.008 per unit plus 50 percent benefits. Up-front engineering and design costs will amount to $40,000. Finally, management has insisted that overhead be allocated if the parts are made in-house at a rate of 100 percent of direct labor wage costs. The firm uses a cost of capital of 15 percent per year.
a. Calculate the difference in NPVs between the Make and Buy options. Express all costs as positive values in your calculations. It is suggested to use the NPV function in Excel. (Do not round intermediate calculations. Round your answer to 2 decimal places.)
b. Should you continue to produce in-house or accept the bid from your Taiwanese supplier?
multiple choice
Produce in-house
Accept the bid

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Project Management Made Simple

Authors: Terry Schmidt

1st Edition

0470411589, 978-0470411582

More Books

Students also viewed these General Management questions