One operator loads and unloads five machines. Service duration is 12 minutes per machine and each machine can operate for 80 minutes between loading and
One operator loads and unloads five machines. Service duration is 12 minutes per machine and each machine can operate for 80 minutes between loading and unloading. What is the service factor? Multiple Choice 0.130 0.080 0.092 0.172