One technique used to analyse the tasks to control the length of a project is Critical Path Analysis (CPA). If a critical task is delayed

One technique used to analyse the tasks to control the length of a project is Critical Path Analysis (CPA). If a critical task is delayed or extended, the entire project duration is delayed. On the other hand, if the duration of a critical task is shortened, the entire project duration is shortened and the project finish date would move up. The critical path is the group of tasks that together control the length of the project and is made up of critical tasks. By assessing the critical path in a project, a project manager can determine where to focus resources and time to complete the project. Using a relevant example, deliberate on how the project manager can manipulate the critical path in order to ensure project completion should a project derail..

Step by Step Solution

There are 3 Steps involved in it

Step: 1

The critical path is the sequence of tasks that must be completed in order to finish any project This includes the projects start and end dates A crit... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these Human Resource Management questions

Question

Identify the biological causes of amnesia.

Answered: 1 week ago