Question

1 Approved Answer

One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of F.

One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of F. C is made of one unit of D, one unit of E, and two units of F. Items A, B, C, and D have 20, 50, 30, and 25 units of on-hand inventory. Items A, B, and C use lot-for-lot (L4L) as their lot-sizing technique, while D, E, and F require multiples of 50, 100, and 90, respectively, to be purchased. B has scheduled receipts of 20 units in Period 1. No other scheduled receipts exist. Lead times are one period for Items A, B, and D, and two periods for Items C, E, and F. Gross requirements for A are 20 units in Period 1, 10 units in Period 2, 55 units in Period 6, and 50 units in Period 8.

Find the planned order releases for all items. (Leave no cells blank - be certain to enter "0" wherever required.)

image text in transcribed

image text in transcribed \begin{tabular}{|c|c|c|c|c|c|c|c|c|c|} \hline & Period & 1 & 2 & 3 & 4 & 5 & 6 & 7 & 8 \\ \hline & Gross requirements & & & & & & & & \\ \hline Item A & Scheduled receipts & & & & & & & & \\ \hline OH=20 & Projected available balance & & & & & & & & \\ \hline LT=1 & Net requirements & & & & & & & & \\ \hlineSS=0 & Planned order receipts & & & & & & & & \\ \hline \multirow[t]{2}{*}{Q=L4L} & Planned order releases & & & & & & & & \\ \hline & Gross requirements & & & & & & & & \\ \hline Item B & Scheduled receipts & & & & & & & & \\ \hline OH=50 & Projected available balance & & & & & & & & \\ \hline LT=1 & Net requirements & & & & & & & & \\ \hlineSS=0 & Planned order receipts & & & & & & & & \\ \hline \multirow[t]{2}{*}{Q=L4L} & Planned order releases & & & & & & & & \\ \hline & Gross requirements & & & & & & & & \\ \hline Item C & Scheduled receipts & & & & & & & & \\ \hline OH=30 & Projected available balance & & & & & & & & \\ \hline LT=2 & Net requirements & & & & & & & & \\ \hlineSS=0 & Planned order receipts & & & & & & & & \\ \hline \multirow[t]{2}{*}{Q=L4L} & Planned order releases & & & & & & & & \\ \hline & Gross requirements & & & & & & & & \\ \hline \end{tabular} \begin{tabular}{|l|l|l|} \hline Item D & Scheduled receipts \\ \hline OH=25 & Projected available balance \\ \hline LT=1 & Net requirements \\ \hline SS=0 & Planned order receipts \\ \hline Q=50 & Planned order releases \\ \hline Item E & Scheduled receipts \\ \hline OH=0 & Projected available balance & Net requirements \\ \hline LT=2 & Planned order receipts \\ \hline SS=0 & Planned order releases \\ \hline Q=100 & Gross requirements \\ \hline Item F & Scheduled receipts \\ \hline OH=0 & Projected available balance \\ \hline LT=2 & Net requirements \\ \hline SS=0 & Planned order receipts \\ \hline Q=90 & Planned order releases \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Beer Business Finance

Authors: Kary R Shumway

1st Edition

1090833741, 978-1090833747

More Books

Students also viewed these Finance questions