One unit of A is made of one unit of B and one unit of C. B is made of four units of C and
One unit of A is made of one unit of B and one unit of C. B is made of four units of C
and one unit each of E and F. C is made of two units of D and one unit of E. E is made
of three units of F. Item C has a lead time of one week; Items A, B, E, and F have two
week lead times; and Item D has a lead time of three weeks. Lot-for-lot sizing is used
for Items A, D, and E; lots of size 50, 100, and 50 are used for Items B, C, and F,
respectively
Items A, C, D, and E have on-hand (beginning) inventories of 20, 50, 100, and 10,
respectively; all other items have zero beginning inventory. We are scheduled to receive
10 units of A in Week 1, 100 units of C in Week 2, and 100 units of D in Week 3; there
are no other scheduled receipts.
a. Draw the product tree of the end item A, and determine the low-level codes of all the
items in the tree.
b. What is the minimum number of weeks that you should include in the planning
horizon to make the MRP records feasible?
c. Assume for now that there are no scheduled receipts and no beginning inventories
for all the items in the bill of material. How many Fs do you need to make 100 As?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started