Only 1 hour left please give me answers. . (TCO A) A project is a temporary endeavor undertaken to create what three things. (Points :

Only 1 hour left please give me answers.

.(TCO A) A project is a temporary endeavor undertaken to create what three things. (Points : 10)
Unique product, service, or objective Unique project, service, or routine Unique product, service, or result Unique routine, service, or result

Question 2.2.(TCO H) The fundamental purpose of the post-project evaluation is to improve future projects. An important component of this evaluation is (Points : 10)
the project audit. the closure checklist. lessons learned. customer satisfaction report.

Question 3.3.(TCO B) The _____ authorizes the project manager to proceed with the project. (Points : 10)
Project Work Order (PWO) Project Charter Responsibility Assignment Matrix (RAM) Project Funding Authorization

Question 4.4.(TCO D) All of the following are strategies for positive risks except _____. (Points : 10)
share exploit enhance transfer

Question 5.5.(TCO F) The primary purpose of a _____ meeting is to identify and resolve problems. (Points : 10)
communications flow status review technical design review problem solving

Question 6.6.(TCO F) Without _____ no one knows what to do. (Points : 10)
status review communication technical design review ideas

Question 7.7.(TCO C) If _____ is positive, it represents the maximum amount of time that the activities on a particular path can be delayed without jeopardizing the completion of the project by its required completion time. (Points : 10)
total time free float total slack cumulative slack

Question 8.8.(TCO A) The project plan is executed in the _____. (Points : 10)
initiating phase planning phase executing phase closing phase

Question 9.9.(TCO C) Why are activities drawn in a serial relationship on a network diagram? (Points : 10)
The activities use different resources. The activities are independent of each other. From a technical standpoint, the activities must be performed in that sequence. The order of completion doesnt matter.

Question 10.10.(TCO F) The _____ is the amount that was budgeted to accomplish the work scheduled to be performed up to that point in time. (Points : 10)
total budgeted cost (TBC) cumulative actual cost (CAC) cumulative budgeted cost (CBC) cumulative earned value (CEV)

Question 11.11.(TCO C) Calculate the earliest start for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days. (Points : 10)
Day 5 Day 3 Day 1 This cannot be calculated based upon the information given.

Question 12.12.(TCO H) A project audit provides an opportunity to evaluate issues and concerns to determine potential improvements. Some benefits of a project audit are (Points : 10)
reduce project risk, time, and cost overruns. keep the scope of the project under control. allow the project team to have good performance. recommend outsourcing on other projects.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these General Management questions