ONLY ANSWER PROBLEM NUMBER 2 PLEASE!! Problem 1: (10 points) Methods of Estimating Costs: Engineering Estimates Debarge Homebuilders (DH) designs and constructs high-end homes on

ONLY ANSWER PROBLEM NUMBER 2 PLEASE!!

Problem 1: (10 points) Methods of Estimating Costs: Engineering Estimates Debarge Homebuilders (DH) designs and constructs high-end homes on large lots owned by customers. DH has developed several formulas, which it uses to quote jobs.

These include costs for materials, labor, and other costs.

Below are the cost estimates:

Administrative costs $30,000 Building costs-per sq. ft. (basic) 100 Building costs-per sq. ft. (moderate) 165 Building costs-per sq. ft. (luxury) 250 Appliances (basic) 16,000 Appliances (moderate) 28,000 Appliances (luxury) 50.000 Utilities costs 45,000 A customer has expressed interest in having DH build a moderate, 3,200 sq. ft. home on a vacant lot. Based on the engineering estimates above, what will such a house cost to build?

Problem 2: (10 points) Basic Cost Flow Model Fill in the missing items for the following inventories;

Beginning balance $15,300 $34,600 $18,000

Ending balance 13,500 29,000 15,000

Transferred in 45,000

Transferred out 83,000. 20,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Sound Investing, Chapter 10 - One-Time Charges And Other Format Fakes

Authors: Kate Mooney

2nd Edition

0071719326, 9780071719322

More Books

Students also viewed these Accounting questions

Question

Sell the quality of your brand or products.

Answered: 1 week ago