Only relevant costs need to be considered in decision-making situations. Which of the following are relevant costs? 1 Project-specific costs 2 Avoidable future costs 3
Only relevant costs need to be considered in decision-making situations.
Which of the following are relevant costs?
1 Project-specific costs
2 Avoidable future costs
3 Common costs
4 Unavoidable costs
Select one:
a.2 and 4 only
b.1, 2, 3 and 4
c.1, 2 and 3 only
d.1 and 2 only