OPERATIONS RESEARCH Adrian n Ray a research and development company has a project which has a list of tasks to be performed whose time estimates
OPERATIONS RESEARCH
- Adrian n Ray a research and development company has a project which has a list of tasks to be performed whose time estimates are given in the table as follows.
I Activity j | Activity | T0 | tm | tp |
1-2 | A | 4 | 6 | 8 |
1-3 | B | 2 | 3 | 10 |
1-4 | C | 6 | 8 | 16 |
2-4 | D | 1 | 2 | 3 |
3-4 | E | 6 | 7 | 8 |
3-5 | F | 6 | 7 | 14 |
4-6 | G | 3 | 5 | 7 |
4-7 | H | 4 | 11 | 12 |
5-7 | I | 2 | 4 | 6 |
6-7 | J | 2 | 9 | 10 |
- Draw the project network.
- Find the critical path.
- Find the probability that the project is completed in 19 days. If the probability is lessthan 20%, find the probability of completing it in 24 days.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started