Question
1 Approved Answer
Optimistic Most Probable Pessimistic Activity Time Time Time A 4 5 6 B 2 . 5 3 3 . 5 C 6 7 8 D
Optimistic Most Probable Pessimistic
Activity Time Time Time
A
B
C
D
E
F
G
Suppose that the critical path is ACEFG Use Appendix A to answer the questions. Do not round intermediate calculations. Round your answers to three decimal places.
What is the probability that the project will be completed within weeks?
What is the probability that the project will be completed within weeks?
What is the probability that the project will be completed in more than weeks?
What is the probability that the project will be completed in weeks?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3