Option #2: Managing the Construction Project Budget Assume you are managing a construction project with a schedule as shown in the textbook's Figure 3.5b. A
Option #2: Managing the Construction Project Budget
Assume you are managing a construction project with a schedule as shown in the textbook's Figure 3.5b. A budget of $24M has been assigned to it and you have distributed this budget among the project activities as follows:
Percent of Budget Allocated (%) | |
---|---|
Utilities and Site Work | 0.13 |
Structure | 0.35 |
Envelope | 0.15 |
Finishes | 0.08 |
Systems | 0.25 |
Closeout | 0.04 |
Assuming that each project activity will consume it's budget uniformly throughout its duration, develop a cost flow diagram that shows the project budget expendable (per month) and the cumulative amounts (per month) in the form of a histogram that shows the values over time with monthly time periods.
Assuming that project funds will be allocated per the below schedule, develop a cash flow diagram that shows the total funds received and the cumulative amounts in the form of a histogram that shows the amounts received over time with monthly time periods.
Amount of funds allocated at the beginning of period | |
---|---|
December | $5,420,168 |
March | $3,551,597 |
April | $4,361,267 |
May | $7,759,354 |
September | $2,907,615 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started