Question
Option #2: Resource Schedule You have determined the following schedule for a project in which the key resource is a backhoe. You receive a call
Option #2: Resource Schedule
You have determined the following schedule for a project in which the key resource is a backhoe. You receive a call from your partner, Delvin, who desperately needs one of your backhoes for four days. You tell Delvin you would be willing to let him have a backhoe if you are still able to project in 13 days.
Develop a resource schedule in the Resource Load Chart Download Resource Load Chartwhich follows to see if it is possible to lend Delvin a backhoe for four days and still get your project in 13 days. Be sure to record the order in which you schedule the activities, using scheduling heuristics. No splitting of activities is possible.
Can you say yes to Delvin's request? If yes, which days would you lend him the backhoe? If not, why not? Thoroughly address the question but include the chart as an Appendix to your paper.
Can some please help with filling this resource load project I am so confused and having a hard time. Thank you. see attchment.
Schedule the resource load chart with ES and Slack updates 3 2 0 5 ID Res Dur ES LF SLC 1 1 O 3 1 2 2 1 3 2 1 3 1 0 2 2 A A 1 7 0 1 3 A 5 10 0 6 3 6 13 14 15 3 4 13 7 2 7 8 9 10 11 12 3 4 5 6 0 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 Resources scheduled Resources available hipStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started