Question

1 Approved Answer

Order;Time Since Order Arrived ( hours ago ) ;Estimated Machine Time ( hours ) ;Due Date ( hours from now ) The due dates reflect

Order;Time Since Order Arrived (hours ago);Estimated Machine Time (hours);Due Date (hours from now)The due dates reflect the need for the order to be at its next operation. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average past due hours.
Part 2
Using the FCFS(first come, first served) decision rule for sequencing the orders, the order is:
Sequence
1
2
3
4
5
Order
5
3
4
1
2
5
4
2
1
3
5
3
1
2
4
1
2
5
4
3
1
2
4
5
3
Part 3
Using the EDD(earliest due date) decision rule for sequencing the orders, the order is(to resolve a tie, use order in which the orders were received):
Sequence
1
2
3
4
5
Order
2
3
4
5
1
2
4
3
5
1
4
5
2
1
3
2
4
5
1
3
1
5
3
2
4
Part 4
The average flow time and average past due hours for each option are (enter your responses are real numbers rounded to two decimal places):
Rule
Average Flow Time
Average Past Due Hours
EDD
enter your response here
enter your response here
FCFS
enter your response here
enter your response here
1;3;15;18
2;1;9;20
3;0;7;21
4;6;10;12
5;5;3;8
The due dates reflect the need for the order to be at its next operation. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average past due hours.
Part 2
Using the FCFS(first come, first served) decision rule for sequencing the orders, the order is:
Sequence
1
2
3
4
5
Order
5
3
4
1
2
5
4
2
1
3
5
3
1
2
4
1
2
5
4
3
1
2
4
5
3
Part 3
Using the EDD(earliest due date) decision rule for sequencing the orders, the order is(to resolve a tie, use order in which the orders were received):
Sequence
1
2
3
4
5
Order
2
3
4
5
1
2
4
3
5
1
4
5
2
1
3
2
4
5
1
3
1
5
3
2
4
Part 4
The average flow time and average past due hours for each option are (enter your responses are real numbers rounded to two decimal places):
Rule
Average Flow Time
Average Past Due Hours
EDD
enter your response here
enter your response here
FCFS
enter your response here
enter your response here

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Engineering Risk Management

Authors: Genserik Meyer, Thierry, Reniers

3rd Edition

311066531X, 978-3110665314

More Books

Students also viewed these General Management questions