Question
O'Reilly has been approached by a customer who would like a special job to be done for him, and who is willing to pay $22,000
O'Reilly has been approached by a customer who would like a special job to be done for him, and who is willing to pay $22,000 for it. The job would require the following materials.
Material Total units Units already Book value of Realisable Replacement
Required in inventory units in inv. Value Cost
$/unit $/unit $/unit
A 1,000 0 - - 6
B 1,000 600 2 2.50 5
C 1,000 700 3 2.50 4
D 200 200 4 6.00 9
Material B is used regularly by O'Reilly, and if units of B are required for this job, they would need to be replaced to meet other production demand.
Materials C and D are in Inventory as the result of previous over-buying, and they have a restricted use. No other use could be found for material C, but the units of material D could be used in another job as substitute for 300 units of material E, which currently costs $5 per unit (of which the company has no units in Inventory at the moment).
Required
Calculate the relevant costs of material for deciding whether or not to accept the contract.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started