Organizing Scenario: A home owner, Bjorn Bjornson, approaches your company, We Can Build Anything, LLC regarding a construction project. The Mr. Bjornson tells the company
Organizing Scenario:
A home owner, Bjorn Bjornson, approaches your company,We Can Build Anything, LLCregarding a construction project. The Mr. Bjornson tells the company owner, Dan DeMan, that the tornado that came through the area last week destroyed the patio on the back of the homeowner's house. The homeowner has planned a huge soiree for next weekend at his home. It's a work-related cook-out (so it's super important to the homeowner) that the homeowner has planned with lots of people coming, so the homeowner needs to get his wooden patio deck re-built as soon as possible, or at least in time for the soiree. As it is a Monday now, originally the party was planned to occur in two Saturdays. Mr. Bjornson's work and work friends say that it's okay to not have the party in two weeks to take plenty of time needed to get the patio rebuilt. So, the goal now is to build a patio deckand spa on the deck at Bjornson's house by the 2020 Thanksgiving weekend. Considering today's date,Mr. Deman tells your boss, Sheila Kardashian, that he's accepted the job to rebuild the homeowner's deck and place the spa on the deck in time for the 2020 Thanksgiving weekend. Sheila tells your crew that they will do the patio re-build job and according to thePatio Deck Re-Build Project schedule listed below.
Patio Deck Re-Build Project Planning *= A milestone. This isa marked, measurable, and noted action or event toward significant progress regarding a goal or developmental stage during a project. | ||||
Activity | Time (days) | Activity Identity | Activity's Immediate Predecessor (What activity must occur before this one...) | Milestones |
Bidding Phase | ||||
Complete Estimate w/Plans | 7 | A | None | |
Receive City Bidding Permits | 3 | B | A | |
Receive Bid from Excavator 1 | 3 | C | B | |
Receive Bid from Excavator 2 | 4 | D | B | |
Receive Bid from Excavator 3 | 5 | E | B | |
Receive Bid for Concrete (Mason) | 2 | F | B | |
Receive Bid from Carpenter 1 | 6 | G | B | |
Receive Bid from Carpenter 2 | 7 | H | B | |
Receive Bid from Carpenter 3 | 5 | I | B | |
Receive Bid from Plumber 1 | 2 | J | A | |
Receive Bid from Electrical/Mechanical Contractor 1 | 2 | K | B | |
Receive Bid from Electrical/Mechanical Contractor 2 | 3 | L | B | * |
Approval Phase | ||||
Approve Excavator 2 Bid | 2 | M | C,D,E | |
Approve Concrete Bidand order concrete per the bid | 1 | N | F | |
Approve Carpenter 1 Bid and order lumber per the bid | 2 | O | G,H,I | |
Approve Plumber Bid | 1 | P | J | |
Approve Mechanical Contractor Bid 1 | 2 | Q | K,L | * |
Work Phase | ||||
Excavate Patio Foundation (Excavator) | 3 | R | M,N | |
Pour Concrete Footings (Mason) | 1 | S | R | |
Concrete Cure Time (Mason) | 7 | T | S | |
Construct Patio (Except Railing) (Carpenter) | 4 | U | O, T | |
Install Spa (Mechanical Contractor) | 3 | V | U | |
Install Plumbing (Plumber) | 4 | W | P | |
Wire Electrical (Mechanical Contractor) | 1 | X | Q | |
Complete Patio (Railing Completed), Landscape (Me) | 4 | Y | T,U | |
Ordering/Order Acceptance Phase | ||||
Order Spa | 1 | Z | A,B | |
Order BOM Components for Carpenter | 1 | AA | A,B,O | |
Receive Spa | 7 | BB | Z | |
Receive BOM Components | 9 | CC | AA | |
Payment Phase | * | |||
Receive Bill, Pay Excavator | 15 | DD | R | |
Receive Bill, Pay Mason | 30 | EE | T | |
Receive Bill, Pay Carpenter | 15 | FF | U | |
Receive Bill, Pay Plumber | 30 | GG | W | |
Receive Bill, Pay Mechanical Contractor | 30 | HH | V, X | |
Utilization Phase | * | |||
Break-in Spa | 2 | II | X | |
Patio Party | JJ | II | * |
Directions: Develop a goal statement for this project that is specific, measurable, achievable, relevant, and time bound for organizing scenario below. Explain why the goal statement is specific, measurable, achievable, relevant, and time-bound. Use the SMART Goal Setting Method to develop it.Provide your goal statement, rationale, Gantt chart for progress toward project completion, and consider wages, tools, and materials cost to determine a productivity ratio. Submit this assignment by the due date and time.
----------------------------------------------------------------------------------------
1) Provide a goal statement for project described above, below.
2) Provide your rationale that the goal statement is specific, measurable, achievable, relevant and time-bound below.
3) Produce a Gantt chart detailing the 5 major phases of the construction project above.
4) Since Productivity = Output / Labor + Capital + Materials:
a) What tools and materials do you think an excavator(s) might use to do this job? How much will tools and materials cost?
b) What tools and materials might a mason(s) use to do this job? How much will tools and materials cost?
c) What tools and materials might a carpenter(s) use to do this job?How much will tools and materials cost?
d) What tools and materials might an Electrical/ Mechanical contractor(s) use to do this job? How much will tools and materials cost?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started