Oriel ink began work on 107000 known conceivable contract in 2023 to construct an office building during 2023 or real incurred cost of 135200 build
Oriel ink began work on 107000 known conceivable contract in 2023 to construct an office building during 2023 or real incurred cost of 135200 build its customers for 12000 non refundable and collected 910008. December 31st 2023 the estimated future caused to complete the project totaled 384800 prepare or real 2023 journal. No entries using the percentage of completion method