Oriole Construction is constructing an olfice building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1700000 each quarter. The total contract price is $20400000 and Oriole estimates total costs of $17900000. Oriole estimates that the building will take 3 years to complete, and commences construction on January 2, 2021. At December 31, 2022, Oriole Construction estimates that it is 75% complete with the building: however, the estimate of total costs to be incurred has risen to $18150000 due to unanticipated price increases. Oriole Construction completes the remaining 25% of the building construction on December 31,2023 , as scheduled. At that time the total costs of construction are $18900000. What is the total amount of Revenue from Long-Term Contracts and Construction Expenses that Oriole will recognize for the year ended December 31, 2023? Oriole Construction is constructing an olfice building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1700000 each quarter. The total contract price is $20400000 and Oriole estimates total costs of $17900000. Oriole estimates that the building will take 3 years to complete, and commences construction on January 2, 2021. At December 31, 2022, Oriole Construction estimates that it is 75% complete with the building: however, the estimate of total costs to be incurred has risen to $18150000 due to unanticipated price increases. Oriole Construction completes the remaining 25% of the building construction on December 31,2023 , as scheduled. At that time the total costs of construction are $18900000. What is the total amount of Revenue from Long-Term Contracts and Construction Expenses that Oriole will recognize for the year ended December 31, 2023