Oriole Ltd. uses 4,410 meters of fine gauge brass each year. Brass wire costs $12 per meter, ordering costs are $44 per order, and carrying

Oriole Ltd. uses 4,410 meters of fine gauge brass each year. Brass wire costs $12 per meter, ordering costs are $44 per order, and carrying costs are $2.20 per meter. Currently, Oriole orders 700 meters in each order. Is this the most economical order size? If not, what is the economic order quantity? How much will Oriole save using the EOQ? (Round answers to 2 decimal places, e.g. 125.74.)

Economic order quantity=

meters
Oriole will save= $

per year

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting The Cornerstone Of Business Decision-making, , (6 Months)

Authors: Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger

7th Edition

1337115924, 9781337115926

More Books

Students also viewed these Accounting questions

Question

Why do companies need competent workers for good internal control?

Answered: 1 week ago

Question

What is the use of bootstrap program?

Answered: 1 week ago

Question

What is a process and process table?

Answered: 1 week ago

Question

What is Industrial Economics and Theory of Firm?

Answered: 1 week ago

Question

Can you see what limitations your purpose imposes on your strategy?

Answered: 1 week ago