Ornamental Sculptures Mfg . manufactures garden sculptures. Each sculpture requires 9 pounds of direct materials al a cost of $ 4 per pound and 0
Ornamental Sculptures Mfg manufactures garden sculptures. Each sculpture requires pounds of direct materials al a cost of $ per pound and direct labor hours at a rate of $ per hour. Variable manufacturing overhead is charged at a rate of $ per direct labor hour. Fixed manufacturing overhead is $ per month. The company's policy is to maintain direct materials inventory equal to of the next month's materials requirement. At the end of February the company had pounds of direct materials in inventory. The company's production budget reports the following.
tableProduction Budget,March,April,MayUnits to be produced,
Prepare direct materials budgets for March and April.
Prepare direct labor budgets for March and April.
Prepare factory overhead budgets for March and April.
Complete this question by entering your answers in the tabs below.
Prepare direct materials budgets for March and April.
tableORNAMENTAL SCULPTURES MFGDirect Materials BudgetFor the Months of March and AprilBudgeted production unitsMarch,AprilMaterials requirements per unit IbsMaterials needed for production IbsBudgeted ending inventory IbsTotal materials requirements IbsBudgeted beginning inventory IbsOrnamental Sculptures Mfg manufactures garden sculptures. Each sculpture requires pounds of direct materials al a cost of $ per pound and direct labor hours at a rate of $ per hour. Variable manufacturing overhead is charged at a rate of $ per direct labor hour. Fixed manufacturing overhead is $ per month. The company's policy is to maintain direct materials inventory equal to of the next month's materials requirement. At the end of February the company had pounds of direct materials in inventory. The company's production budget reports the following.
tableProduction Budget,March,April,MayUnits to be produced,
Prepare direct materials budgets for March and April.
Prepare direct labor budgets for March and April.
Prepare factory overhead budgets for March and April.
Complete this question by entering your answers in the tabs below.
Prepare direct materials budgets for March and April.
tableORNAMENTAL SCULPTURES MFGDirect Materials BudgetFor the Months of March and AprilBudgeted production unitsMarch,AprilMaterials requirements per unit IbsMaterials needed for production IbsBudgeted ending inventory IbsTotal materials requirements IbsBudgeted beginning inventory Ibs
Ornamental Sculptures Mfg manufactures garden sculptures. Each sculpture requires pounds of direct materials at a cost of $ per pound and direct labor hours at a rate of $ per hour. Variable manufacturing overhead is charged at a rate of $ per direct labor hour. Fixed manufacturing overhead is $ per month. The company's policy is to maintain direct materials inventory equal to of the next month's materials requirement. At the end of February the company had pounds of direct materials in inventory. The company's production budget reports the following.
tableProduction Budget,March,April,MayUnits to be produced,
Prepare direct materials budgets for March and April.
Prepare direct labor budgets for March and April.
Prepare factory overhead budgets for March and April.
Complete this question by entering your answers in the tabs below.
Required
Prepare direct labor budgets for March and April. Round DL hours required per unit" answers to two decimal places.
tableORNAMENTAL SCULPTURES MFGDirect Labor BudgetFor the Months of March and April,Budgeted production unitsDL hours required per unit,,Total direct labor hours needed,,AprilDirect labor rate per hour,,
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started