Orville Company's standard and actual costs per unit are provided below for the most recent period. During this time period 640 units were actually produced.

Orville Company's standard and actual costs per unit are provided below for the most recent period. During this time period 640 units were actually produced.

Standard

Actual

Materials:

Standard: 2.4 metres at $2.5 per m.

$6.00

Actual: 2.1 metres at $2.60 per m.

$5.46

Direct labour:

Standard: 1.5 hrs. at $8.30 per hr.

12.45

Actual: 1.7 hrs. at $8.50 per hr.

14.45

Variable overhead:

Standard: 1.5 hrs. at $4.60 per hr.

6.90

Actual: 1.7 hrs. at $4.20 per hr.

7.14

Total unit cost

$25.35

$27.05

For simplicity, assume there was no inventory of materials at the beginning or end of the period.

Given the information above, compute the following variances. Also indicate if the variances are favorable or unfavorable.

1.Materials price variance

2.Materials quantity variance

3.Direct labour rate variance

4.Direct labour efficiency variance

5.Variable overhead efficiency variance

6.Variable overhead spending variance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Cost Management Measuring Monitoring And Motivating Performance

Authors: Leslie G. Eldenburg, Susan Wolcott, Liang Hsuan Chen, Gail Cook

2nd Canadian Edition

1118168879, 9781118168875

Students also viewed these Accounting questions