Outsourcing (Make-or-Buy) Decision Mountain Air Limited manufactures a line of room air purifiers. Management is currently evaluating the possible production of an air purifier for

Outsourcing (Make-or-Buy) Decision

Mountain Air Limited manufactures a line of room air purifiers. Management is currently evaluating the possible production of an air purifier for automobiles. Based on an annual volume of 10,000 units, the predicted cost per unit of an auto air purifier follows.

Direct materials$8.00Direct labor1.50Factory overhead6.00Total$15.50

These cost predictions include $50,000 in facility-level fixed factory overhead averaged over 10,000 units.

One of the component parts of the auto air purifier is a battery-operated electric motor. Although the company does not currently manufacture these motors, the preceding cost predictions are based on the assumption that it will assemble such a motor. Mini Motor Company has offered to supply an assembled battery-operated motor at a cost of $3.50 per unit, with a minimum annual order of 5,000 units. If Mountain Air accepts this offer, it will be able to reduce the variable labor and variable overhead costs of the auto air purifier by 50 percent. The electric motor's components will cost $2.00 if Mountain Air assembles the motors.

(a) Determine whether Mountain Air should continue to make the electric motor or outsource it from Mini Motor Company.

  • Calculate the net advantage (disadvantage)of outsourcing the electric motors from Mini Motor Company.
  • Use a negative sign with your answer to indicate a net disadvantage (if applicable).
  • $Answer

(b) If it could otherwise rent the motor-assembly space for $21,000 per year, should it make or outsource this component?

  • Calculate the netadvantage (disadvantage)of outsourcing themotors, assuming thespace could be rented.
  • Use a negative sign with your answer to indicate a net disadvantage (if applicable).
  • $Answer

(c) Management should consider which of the following nonquantitative factors in deciding whether to make or buy the motors.

The quality of their own and the supplier's motors.

The dependability of the supplier.

Whether Mini Motor has a track record of meeting its commitments.

Whether they can depend on Mini Motor to supply motors for a number of years or whether it is attempting to use some temporarily idle capacity.

All of these.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Jennifer Cainas, Celina J. Jozsi, Kelly Richmond Pope

1st Edition

0137689454, 9780137689453

Students also viewed these Accounting questions

Question

In each part, find Re (z) and Im (z). (a) z = 3ei (b) |= 2ei/2|

Answered: 1 week ago

Question

Debate the overexpansion of mental disorders attributed to the DSM.

Answered: 1 week ago