. Over Building Corp. has an $8 million contract to construct a building. The company estimates $5.2 million in costs to construct the building and
. Over Building Corp. has an $8 million contract to construct a building. The company estimates $5.2 million in costs to construct the building and an expected gross profit of $2.8 million. During the current year, the company incurred $1,560,000 of costs on the contract. Under the percentage-of-completion method, how much will Over Building Corp. report as revenue in the current year?