Overhead Budget Johnston Company cleans and applies powder coat paint to metal items on a job-order basis. Johnston has budgeted the following amounts for various

Overhead Budget

Johnston Company cleans and applies powder coat paint to metal items on a job-order basis. Johnston has budgeted the following amounts for various overhead categories in the coming year.

Supplies $212,000
Gas 53,000
Indirect labor 174,000
Supervision 75,000
Depreciation on equipment 48,000
Depreciation on the buliding 45,000
Rental of special equipment 10,000
Electricity (for lighting, heating, and air conditioning) 27,500
Telephone 5,000
Landscaping service 1,600
Other overhead 56,000

In the coming year, Johnston expects to powder coat 200,000 units. Each unit takes 1.4 direct labor hours. Johnston has found that supplies and gas (used to run the drying ovensall units pass through the drying ovens after powder coat paint is applied) tend to vary with the number of units produced. All other overhead categories are considered to be fixed.

Required:

1. Calculate the number of direct labor hours Johnston must budget for the coming year. Calculate the variable overhead rate. Calculate the total fixed overhead for the coming year. When required, round your answers to the nearest cent and use the rounded answers in subsequent requirements.

Direct labor hours
Variable overhead rate $ per direct labor hour
Total fixed overhead $

Feedback

Partially correct

2. Prepare an overhead budget for Johnston for the coming year. Show the total variable overhead, total fixed overhead, and total overhead. When required, round your answers to the nearest cent.

Johnston Company
Overhead Budget
For the Coming Year
Budgeted direct labor hours
Variable overhead rate $
Budgeted variable overhead $
Budgeted fixed overhead
Total budgeted overhead $

Feedback

See Cornerstone 8.5.

Calculate the fixed overhead rate and the total overhead rate. If required, round your answers to the nearest cent.

Fixed overhead rate $ per direct labor hour
Total overhead rate $ per direct labor hour

Feedback

See Cornerstone 8.5.

3. What if Johnston had expected to make 198,000 units next year? Assume that the variable overhead per unit does not change and the total fixed overhead amounts do not change. Calculate the new budgeted direct labor hours.

Feedback

Consider the new labor rate and calculate new amounts. Only the direct labor hours change. Prepare a new budget.

Prepare a new overhead budget. If required, round your answers to the nearest cent.

Johnston Company
New Overhead Budget
For the Coming Year
Budgeted direct labor hours
Variable overhead rate $
Budgeted variable overhead $
Budgeted fixed overhead
Total budgeted overhead $

Feedback

Consider the new labor rate and calculate new amounts. Only the direct labor hours change. Prepare a new budget.

Calculate the fixed overhead rate and the total overhead rate. If required, round your answers to the nearest cent.

Fixed overhead rate $ per direct labor hour
Total overhead rate $ per direct labor hour

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Ray Garrison, Eric Noreen, Peter Brewer

16th edition

1259307417, 978-1260153132, 1260153134, 978-1259307416

Students also viewed these Accounting questions