Answered step by step
Verified Expert Solution
Question
1 Approved Answer
- Overhead was applied to jobs using a predetermined rate per labor dollar that has been used since the company began operations. - All direct
- Overhead was applied to jobs using a predetermined rate per labor dollar that has been used since the company began operations. - All direct materials were purchased for cash and charged directly to Work-in-Process Inventory when purchased. Direct materials purchased in April amounted to $17,760. - Direct labor costs charged to jobs in April were $125,200. All labor costs were the same per hour for all laborers for April. Required: Calculate the following: a. The cost elements (materials, labor, and overhead) of cost of goods sold before adjustment for over-or underapplied overhead for each job sold. b. The value of each cost element (materials, labor, and overhead) for each job in work-in-process inventory at April 30. c. Over-or underapplied overhead for April. The cost elements (materials, labor, and overhead) of cost of goods sold before adjustment for over- or underapplied overhead for each job sold. Plainview Paving Contractors (PPC) is a rapidly growing, recently established company that has not been profitable despite increases in sales. It has hired you as a consultant to find ways to improve profitability. You believe that the problem results from poor cost control and inaccurate cost estimation on jobs. The company has essentially no accounting system from which to collect data. You are able, however, to piece together the following information for April: - Production 1. Completed Job 33. 2. Started and completed Job 41. 3. Started Job 42. - Inventory Values Work-in-process inventory (excluding applied overhead): - Job 33 was exactly 60 percent complete as to labor on March 31. - Job 42 was exactly 40 percent complete as to labor on April 30. - All direct materials necessary to do the entire job were charged to each job as soon as it was started. - There were no direct materials inventories or finished goods inventories at either March 31 or April 30. - Actual overhead was $121,200. - Cost of goods sold (before adjustment for over-or underapplied overhead): Over- or underapplied overhead for April. Required A Required B [ Required C The value of each cost element (materials, labor, and overhead) for each job in work-in-process inventory at April 30. \begin{tabular}{|l|c|} \hline & Job 42 \\ \hline Materials & \\ \hline Labor & \\ \hline Overhead & \\ \hline \end{tabular} - Overhead was applied to jobs using a predetermined rate per labor dollar that has been used since the company began operations. - All direct materials were purchased for cash and charged directly to Work-in-Process Inventory when purchased. Direct materials purchased in April amounted to $17,760. - Direct labor costs charged to jobs in April were $125,200. All labor costs were the same per hour for all laborers for April. Required: Calculate the following: a. The cost elements (materials, labor, and overhead) of cost of goods sold before adjustment for over-or underapplied overhead for each job sold. b. The value of each cost element (materials, labor, and overhead) for each job in work-in-process inventory at April 30. c. Over-or underapplied overhead for April. The cost elements (materials, labor, and overhead) of cost of goods sold before adjustment for over- or underapplied overhead for each job sold. Plainview Paving Contractors (PPC) is a rapidly growing, recently established company that has not been profitable despite increases in sales. It has hired you as a consultant to find ways to improve profitability. You believe that the problem results from poor cost control and inaccurate cost estimation on jobs. The company has essentially no accounting system from which to collect data. You are able, however, to piece together the following information for April: - Production 1. Completed Job 33. 2. Started and completed Job 41. 3. Started Job 42. - Inventory Values Work-in-process inventory (excluding applied overhead): - Job 33 was exactly 60 percent complete as to labor on March 31. - Job 42 was exactly 40 percent complete as to labor on April 30. - All direct materials necessary to do the entire job were charged to each job as soon as it was started. - There were no direct materials inventories or finished goods inventories at either March 31 or April 30. - Actual overhead was $121,200. - Cost of goods sold (before adjustment for over-or underapplied overhead): Over- or underapplied overhead for April. Required A Required B [ Required C The value of each cost element (materials, labor, and overhead) for each job in work-in-process inventory at April 30. \begin{tabular}{|l|c|} \hline & Job 42 \\ \hline Materials & \\ \hline Labor & \\ \hline Overhead & \\ \hline \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started