P 1 1 - 1 Drawing simple CPM diagram and determining critical path From the following information draw a network showing the critical path and

P11-1 Drawing simple CPM diagram and determining critical path
From the following information draw a network showing the critical path and calculate the minimum time required to complete the work.
\table[[Activity,Duration (days)],[A,1],[B,2],[C,3],[D,1],[E,8],[F,3],[G,2],[I,1]]
A must be completed before starting the other activities, B, C and E can commence concurrently after completion of A. D can commence after completion of B and C. F can commence after completion of C and E. G follows F, and H follows D. I can commence after completion of G and H. Number your nodes.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting 2007 FASB Update Volume 1

Authors: Donald E. Kieso, Jerry J. Weygandt, Terry D. Warfield

12th Edition

0470128755, 978-0470128756

More Books

Students also viewed these Accounting questions