P 1 1 - 2 CPM diagram and determine critical path The following information relates to a project. Predecessors indicate what activities must be completed

P11-2 CPM diagram and determine critical path
The following information relates to a project. Predecessors indicate what activities must be completed before the activity on the left is started. Note that if there are no predecessors (eg activities A, B and C have none) it means they can commence concurrently.
\table[[Activity,Predecessors,Time (days)],[A,-,4],[B,-,10],[C,-,2],[D,B,20],[E,A,D,6],[F,C,12],[G,E,F,16]]
Required:
(a) Draw the network diagram.
(b) List the paths in the network and identify the critical path.
11/Project Management
18 of 21
(c) What is the total project completion time?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Intermediate Accounting 2007 FASB Update Volume 1

Authors: Donald E. Kieso, Jerry J. Weygandt, Terry D. Warfield

12th Edition

0470128755, 978-0470128756

More Books

Students also viewed these Accounting questions

Question

Distinguish between recruitment sources and recruitment methods.

Answered: 1 week ago

Question

How has social media emerged as an important force in recruiting?

Answered: 1 week ago

Question

5.5 Summarize external recruitment methods.

Answered: 1 week ago