P Miller Contractors received a contract to construct a healthcare facility for $3,500,000. Construction began in 2024 and was completed in 2025. Costs and other
P Miller Contractors received a contract to construct a healthcare facility for $3,500,000. Construction began in 2024 and was completed in 2025. Costs and other data are presented below:
2024 | 2025 | ||
Cost incurred during the year | 1,500,000 | 1,300,000 | |
Estimated costs to complete | 1,200,000 | - | |
Billings during the year | 1,700,000 | 1,800,000 | |
Cash Collections during the year | 1,000,000 | 2,500,000 |
Assume that P Miller Contractors uses the percentage-of-completion method for revenue recognition.
1. Compute the amount of gross profit recognized during 2024 and 2025.
2. Prepare all journal entries to record costs, billings, collections and profit recognition for 2024 and 2025. Round your answers to the nearest whole dollar.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started