P11-1 What is the materials price variance? A $ (1,020) U B $ 1,020 F C $ (1,500) U D $ 1,500 F P11-1 What
P11-1 | What is the materials price variance? |
A | $ (1,020) U |
B | $ 1,020 F |
C | $ (1,500) U |
D | $ 1,500 F |
P11-1 | What is the materials quantity variance? |
A | $ 1,400 F |
B | $ (2,100) U |
C | $ 1,300 F |
D | $ (1,300) U |
P11-1 | What is the total materials variance? |
A | $ 2,420 F |
B | $ (2,420) U |
C | $ 3,500 F |
D | $ (3,120) U |
P11-1 | What is the labor price variance? |
A | $ (2,700) U |
B | $ 2,700 F |
C | $ (3,700) U |
D | $ 3,750 F |
P11-1 | What is the labor quantity variance? |
A | $ 4,080 F |
B | $ (4,080) U |
C | $ 3,360 F |
D | $ (3,450) U |
P11-1 | What is the total labor variance? |
A | $ (340) U |
B | $ 330 F |
C | $ 250 F |
D | $ (250) U |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started