Question

1 Approved Answer

PA 4 - 6 ( Algo ) Atlas Incorporated is a toy bicycle manufacturing... Atlas Incorporated is a toy bicycle manufacturing company producing a five

PA 4-6(Algo) Atlas Incorporated is a toy bicycle manufacturing...
Atlas Incorporated is a toy bicycle manufacturing company producing a five-inch small version of the bike that Lance Armstrong rode
to win his first Tour de France. The assembly line at Atlas Incorporated consists of seven work stations, each performing a single step.
Stations and processing times are summarized here:
Step 1(30 seconds): The plastic tube for the frame is cut to size.
Step 2(15 seconds): The tube is put together.
Step 3(30 seconds): The frame is glued together
Step 4(25 seconds): The frame is cleaned.
Step 5(30 seconds): Paint is sprayed onto the frame.
Step 6(40 seconds): Wheels are assembled.
Step 7(35 seconds): All other parts are assembled to the frame.
Under the current process layout, workers are allocated to the stations as shown here:
Worker 1: Steps 1 and 2
Worker 2: Steps 3 and 4
Worker 3: Step 5
Worker 4: Step 6
Worker 5: Step 7
Assume the workers are paid $15 per hour. Each bicycle is sold for $7 and includes parts that are sourced for $1. The company has
fixed costs of $225 per hour. Despite Lance Armstrong's doping confession, there exists substantially more demand for the bicycle
than Atlas can supply.
Note: Do not round intermediate calculations. Round all answers to 2 decimal places. Negative values should be
indicated/inputted with a minus sign.
a. What is the cost of direct labor for the bicycle?
b. How much profit does the company make per hour?
Profit
per hour
c. What would be the profits per hour if Atlas would be able to source the parts 12 percent cheaper ( $0.88 for the parts of one unit)?
Profit
per hour
d. What would be the profits per hour if Atlas were able to reduce fixed costs by 12 percent (to $198 per hour)?
Profit
per hour
e. What would be the profit per hour if Atlas were able to reduce the processing time at the bottleneck by 4 seconds per unit (assume
unlimited demand)?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Understanding Management

Authors: Richard L Daft, Dorothy Marcic

6th Edition

9780324581782, 324581785, 978-0324568387

More Books

Students also viewed these General Management questions