Pagley Company's standard labour cost of producing one unit of product DD is 3.45 hours at the rate of $14.70 per hour. During August, 47,570
Pagley Company's standard labour cost of producing one unit of product DD is 3.45 hours at the rate of $14.70 per hour. During August, 47,570 hours of labour are incurred at a cost of $15.00 per hour to produce 13,400 units of product DD. (a) Your answer correct Calculate the total labour variance. 33969 Total labour variance Unfavourable SHOW SOLUTION LINK TO TEXT (b) Calculate the labour price and quantity variances. Labour price variance: Labour quantity variance: $