Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Paige Turned recently purchased a block of land to building a new multi-million dollar manufacturing plant. The current facility (a converted chemical shed) is consistently

Paige Turned recently purchased a block of land to building a new multi-million dollar manufacturing plant. The current facility (a converted chemical shed) is consistently causing problems. The new purpose-built facility would allow Picasso to increase production and satisfy safety and environmental regulations.

A building consultant has broken the project into a number of separate tasks identified by letters. Preliminary estimates of the normal time and cost have been provided:

Task

Task description

Time (days)

Cost ($)

Crash time (days)

Per day revised costs ($)

A

Preparation of drawings and permits

14

72,500

10

10,000

B

Calling and letting of tenders

68

166,750

66

23,000

C

Site preparation and excavation

6

116,000

4

16,000

D

Pouring the foundation

24

250,000

24

-

E

Framing

40

145,000

30

20,000

F

Plumbing and electrical work

18

159,500

12

22,000

G

Interior finished

16

108,750

12

15,000

H

Exterior finishes

22

175,000

22

-

I

Installing and commissioning new machines

34

101,500

30

14,000

J

Finishing touches and final work through

32

64,000

32

-

The building consultant has advised that the following relationship exists among these tasks:

A and B can be commenced at the same time.

C and D can both be commenced as soon as A is completed.

E cannot be commended until C and D are completed.

F can be commenced once D is completed.

G can be started once F is finished.

H cannot be commenced until E and G are completed.

I cannot start until B and E are completed.

J cannot commence until H and I are completed.

Required:

  1. Using an appropriate computer drawing program, draw the network diagram for the project showing the task letter on the activity paths. (3 marks)
  2. Identify all the possible pathways and determine the critical path. (2 marks)
  3. Calculate the minimum time and associate cost in which the project could be completed. (8 marks)
  4. The building is nearing completion, Paige Turner has written into the contract penalty provisions if the work is not finished on time. The only remaining task to complete is J and so far it is on schedule to complete in time however there is still 12 days to go, the cost has increased from $2,000 per day to $3,500 per day. The building consultant, in discussion with Paige, feels that an investigation might be worthwhile. The cost to investigate is $4,000 per day which might show if there is problem and if this the case it can be rectified by $10,000. This would lead to the cost being reduced to $2,000 for the remaining days. The probability of being able to rectify the problem is 0.7, should the consultant investigate? (7 marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Horngrens Financial & Managerial Accounting, The Financial Chapters

Authors: Tracie Miller Nobles, Brenda Mattison

7th Edition

0136505279, 9780136505273

More Books

Students also viewed these Accounting questions

Question

What penalty (if any) should Foster receive?

Answered: 1 week ago

Question

=+1. What is the schedule for this project?

Answered: 1 week ago