PAL Enterprise manufactures cars with the following assembly line: Production time is 4 5 0 minutes per day, and 1 0 0 cars are required

PAL Enterprise manufactures cars with the following assembly line: Production time is 450 minutes per day, and 100 cars are required per day. Determine the following:
A. Cycle time
B. Theoretical required minimum number of stations
C. Efficiency of the assembly line
\table[[,,],[Task,Predecessors,Time (Minutes)],[A,None,2.5],[B,A,1],[C,None,4],[D,A, C,1],[E,D,1],[F,E,1],[G,B,1],[H,F,G,1]]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Leadership In Health Services Management

Authors: Karien Jooste

2nd Edition

0702180343, 9780702180347

More Books