Question
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four
Panamint Systems Corporation is estimating activity costs associated with producing disk drives, tapes drives, and wire drives. The indirect labor can be traced to four separate activity pools. The budgeted activity cost and activity base data by product are provided below.
Activity Cost
Activity BaseProcurement$356,100Number of purchase ordersScheduling213,100Number of production ordersMaterials handling460,700Number of movesProduct development729,800Number of engineering changesProduction1,515,600Machine hours
Number of
Purchase
Orders
Number of
Production
Orders
Number
of
Moves
Number of
Engineering
Changes
Machine
Hours
Number
of
UnitsDisk drives4,2003501,270151,8002,400Tape drives2,50013564048,2004,100Wire drives11,8009804,5002311,9002,300
The activity-based cost for each wire drive unit is
a.$833.20
b.$19.25
c.$253.44
d.$183.12
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started