Paragraph Styles An IT software project comprises the following activities, whose time estimates are giver against each other as below: Activity Estimated Duration (weeks) Optimistic

image text in transcribed
Paragraph Styles An IT software project comprises the following activities, whose time estimates are giver against each other as below: Activity Estimated Duration (weeks) Optimistic Most Likely Pessimistic 15 1-2 14 1-3 2 30 1-4 6 12 2-5 5 8 2-6 5 17 15 3-6 27 4-7 5-7 6-7 19 28 a) Find the critical path for the project. (10 marks) [Answer and show workings here]

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Project Management

Authors: Jack Gido, Jim Clements , Rose Baker

7th Edition

1337095478, 978-1337095471

More Books

Students also viewed these General Management questions

Question

What made you decide on this subfield of psychology?

Answered: 1 week ago