Part 1) Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $6.00 per Ib.) $ 24.00
Part 1) Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $6.00 per Ib.) $ 24.00 Direct labor (1.8 hrs. @ $11.00 per hr.) 19.80 Overhead (1.8 hrs. @ $18.50 per hr.) 33.30 Total standard cost $ 77.10 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factorys capacity of 20,000 units per month. Following are the companys budgeted overhead costs per month at the 75% capacity level. Overhead Budget (75% Capacity) Variable overhead costs Indirect materials $ 15,000 Indirect labor 75,000 Power 15,000 Repairs and maintenance 30,000 Total variable overhead costs $ 135,000 Fixed overhead costs DepreciationBuilding 24,000 DepreciationMachinery 70,000 Taxes and insurance 17,000 Supervision 253,500 Total fixed overhead costs 364,500 Total overhead costs $ 499,500 The company incurred the following actual costs when it operated at 75% of capacity in October. Direct materials (61,000 Ibs. @ $6.20 per lb.) $ 378,200 Direct labor (21,000 hrs. @ $11.30 per hr.) 237,300 Overhead costs Indirect materials $ 41,750 Indirect labor 176,200 Power 17,250 Repairs and maintenance 34,500 DepreciationBuilding 24,000 DepreciationMachinery 94,500 Taxes and insurance 15,300 Supervision 253,500 657,000 Total costs $ 1,272,500 Required: 1&2. Prepare flexible overhead budgets for October showing the amounts of each variable and fixed cost at the 65%, 75%, and 85% capacity levels and classify all items listed in the fixed budget as variable or fixed.
Part 2) Compute the direct materials cost variance, including its price and quantity variances. AQ = Actual Quantity SQ = Standard Quantity AP = Actual Price SP = Standard Price
Part 3) Compute the direct labor cost variance, including its rate and efficiency variances. AH = Actual Hours SH = Standard Hours AR = Actual Rate SR = Standard Rate
Part 4) Prepare a detailed overhead variance report that shows the variances for individual items of overhead.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started