Question

1 Approved Answer

Part 1 Midwest Rocks receives and produces an order. What is the company's cycle time assuming the following times were measured during production of this

Part 1

Midwest Rocks receives and produces an order. What is the company's cycle time assuming the following times were measured during production of this order?

Process time: .7 days Inspection time: .25 days Move time: 1.05 days Wait time: .5 days

1.8 days

.7 days

.95 days

2 days

2.5 days

Part 2

Midwest Rocks receives and produces an order. What is the company's value-added time assuming the following times were measured during production of this order?

Process time: .7 days Inspection time: .25 days Move time: 1.05 days Wait time: .5 days

1.8 days

.7 days

.95 days

2 days

2.5 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Cost Accounting

Authors: William N. Lanen, Shannon Anderson, Michael W Maher

6th edition

1259969479, 1259565408, 978-1259969478

More Books

Students also viewed these Accounting questions

Question

Outline the five steps in a simple linear regression analysis.

Answered: 1 week ago