part 1) One weakness of CPI is that it cannot be calculated until all the costs for a specific analysis period have been entered into

part 1)

One weakness of CPI is that it cannot be calculated until all the costs for a specific analysis period have been entered into the accounting system. Because suppliers and subcontractors usually bill the project at the end of the month, the CPI can only be calculated monthly, limiting its use as a cost control tool.

Group of answer choices

true

false

part 2)

A LCPI greater than 1.0 does not necessarily mean the project cost is under the budget as it ignores materials, subcontractor, and equipment costs.

Group of answer choices

true

false

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Corporate Financial Management

Authors: Glen Arnold

4th Edition

0273719068, 978-0273719069

More Books

Students also viewed these Finance questions