part 1) One weakness of CPI is that it cannot be calculated until all the costs for a specific analysis period have been entered into
part 1)
One weakness of CPI is that it cannot be calculated until all the costs for a specific analysis period have been entered into the accounting system. Because suppliers and subcontractors usually bill the project at the end of the month, the CPI can only be calculated monthly, limiting its use as a cost control tool.
Group of answer choices
true
false
part 2)
A LCPI greater than 1.0 does not necessarily mean the project cost is under the budget as it ignores materials, subcontractor, and equipment costs.
Group of answer choices
true
false
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started