Part 1 Using the below rate information and duration information, calculate a schedule and budget estimate for your project, based on resources you had allocated

Part 1 Using the below rate information and duration information, calculate a schedule and budget estimate for your project, based on resources you had allocated during week 4 tutorial.

Project Sponsor 120/hr
Program Manager 120/hr
Project Manager 110/hr
QA Manager 110/hr
Business Process Manager 110/hr
2* Business Analysts 90/hr
Technical Lead 90/hr
Technical Architect 90/hr
Solution Architect 90/hr
Training Lead 90/hr
3* Trainers 70/hr
Test Team Lead 90/hr
2* Testers 70/hr
Development Team Lead 90/hr
4* Developers 70/hr
Web Designers 70/hr

Project Name Level 2 Level 3 Duration
1.1 Initiation 1.1.1 Evaluation & Recommendations 3 weeks
1.1.2 Develop Project Charter 3 weeks
1.1.3 Deliverable: Submit Project Charter 5 days
1.1.4 Project Sponsor Reviews Project Charter 3 days
1.1.5 Project Charter Signed/Approved 2 days
1.2 Planning 1.2.1 Create Preliminary Scope Statement 5 weeks
1.2.2 Determine Project Team 5 weeks
1.2.3 Project Team Kickoff Meeting 5 days
1.2.4 Develop Project Plan 3 weeks
1.2.5 Submit Project Plan 2 weeks
1.2.6 Milestone: Project Plan Approval 1 week
1.3 Execution 1.3.1 Project Kickoff Meeting 5 days
1.3.2 Verify & Validate User Requirements 3 weeks
1.3.3 Design System 7 weeks
1.3.4 Procure Hardware/Software 2 weeks
1.3.5 Install Development System 1 week
1.3.6 Testing Phase 5 weeks
1.3.7 Install Live System 3 weeks
1.3.8 User Training 2 weeks
1.3.9 Go Live 1 week
1.4 Control 1.4.1 Project Management ---------
1.4.2 Project Status Meetings ---------
1.4.3 Risk Management ---------
1.4.4 Update Project Management Plan ---------
1.5 Closeout 1.5.1 Audit Procurement 2 weeks
1.5.2 Document Lessons Learned 2 weeks
1.5.3 Update Files/Records 1 week
1.5.4 Gain Formal Acceptance 1 week
1.5.5 Archive Files/Documents 1 week

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach To Planning Scheduling And Controlling

Authors: Harold Kerzner

12th Edition

1119165350, 9781119165354

More Books

Students also viewed these General Management questions