Question
Part 1 You have been assigned as a project manager for a small construction company and have been assigned your first project. The client feels
Part 1
You have been assigned as a project manager for a small construction company and have been assigned your first project. The client feels they have a basic grasp on their requirements but also feels that they will know more as the project progresses. Using your knowledge of life cycle models, identify two models that may work based on your knowledge of the project.
The scope of the project is as follows:
- Requirement 1: 3 bedrooms
- Requirement 2: 2.5 bathrooms
- Requirement 3: Pool
- Requirement 4: 2 patios, one patio should be enclosed
Using your experience documenting scope, outline the problem/opportunity statement you are trying to solve for, 2-3 success criteria, and any assumptions, risks, or obstacles.
Part 2
Create Work Breakdown Structure (WBS) for the following scope:
- Requirement 1: 3 bedrooms
- Requirement 2: 2.5 bathrooms
- Requirement 3: Pool
- Requirement 4: 2 patios, one patio should be enclosed
Your WBS should be based upon your chosen Life Cycle Methodology and include any deliverables.
Part 3
- Build a network diagram
- Identify the early start, early finish, late start late finish for each activity
- Identify the critical path
- Identify the duration of the critical path
- What is the float of Activity B
- What is the float of Activity H
Activity | Predecessor | Duration in Days |
A | Start | 3 |
B | Start | 6 |
c | A, B | 12 |
D | B | 5 |
E | D | 4 |
F | C | 6 |
G | E,F | 8 |
H | E | 7 |
I | H | 3 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started