Part I. PROBLEM SOLVING Direction: In each of the items below, provide the details/data required A concrete company transports concrete from three plants 1, 2,
Part I. PROBLEM SOLVING
Direction: In each of the items below, provide the details/data required
A concrete company transports concrete from three plants 1, 2, and 3, to three constructions sites A, B, C and D with the following details;
Cost From / To | A | B | C | D | Total Supply |
1 | 19 | 30 | 50 | 10 | 7 |
2 | 70 | 30 | 40 | 60 | 9 |
3 | 45 | 8 | 70 | 20 | 18 |
Total Demand | 5 | 8 | 7 | 14 | 34 |
Requirements;
- Compute for the total transportation cost of the initial solution using least cost cell method.
- Obtain the improved solutions total cost of transportation using Stepping-Stone Method.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started